在生产时我们要生成:借:生产成本-原材料   贷:原材料
生产完成时要生成:借:产成品   贷:生产成本-产品产出
还有其他的分录吧,我不是太懂
那PP和FI集成时,会有哪些配置,产生哪些分录?
谁给个详细的答案吧

最佳答案

查看完整内容

FI-PP integration takes place mainly at these stages- 1) When you create and release the production order, the planned costs will be calliculated from BOM and Routing/Master Recipe master data.-Co document will be generated for Planned postings 2) When you issue goods(Raw materials) to production (against Production order) the FI and CO entries will get generated -CO27 FI Entry- Con ...

最近访客

  • EricCai
    2022-09-20
  • 拼命姑娘
    2021-11-18
  • 77154121
    2021-11-05
  • austain8
    2021-08-03
  • xiaoyuzh
    2021-07-26
  • Bella
    2021-07-23
  • tbb1177
    2021-07-22
  • lulu0824
    2021-05-19
  • Jessieli
    2020-09-27




上一篇:每月盘点财务要做点什么?
下一篇:什么时冻结凭证,什么情况会冻结,冻结和解冻一般会有哪些流程
本楼点评(0) 收起
发表于 2012-10-15 00:00:16 | 显示全部楼层
FI-PP integration takes place mainly at these stages-


1) When you create and release the production order, the planned costs will be calliculated from BOM and Routing/Master Recipe master data.-Co document will be generated for Planned postings


2) When you issue goods(Raw materials) to production (against Production order) the FI and CO entries will get generated -CO27

FI Entry- Consumption A/C Dr

                   To Inventory A/C Cr

CO primary cost postings will be triggered against the cost center.


3) When operations in routings are confirmed , the cost centers in the work centers will be charged with the activity costs

Here secondary cost postings will be triggered in the production cost centers.


4) After final confirmation of the operations, the GRN will takes place against the production order, here also CO and FI documents will be generated -CO11

FI-Entry-

Finished Goods A/C Dr

  To cost of goods produced A/C


5) If the production order is not confirmed fully, we have to run WIP at the month end-KKAO

FI entry- WIP A/C Dr

               To Change in WIP A/ c Cr

The above entry will be reversed at the time of settlement of production order.


6) When the PO is technically completed, then settlement of PO takes place-K088

FI entry-

Price Difference(Goods) A/C

   To cost of goods produced A/C

本楼点评(0) 收起
回复

使用道具 举报

发表于 2012-10-15 08:35:04 | 显示全部楼层
帮顶
本楼点评(0) 收起
回复

使用道具 举报

发表于 2012-10-15 10:04:08 | 显示全部楼层
顶顶顶
本楼点评(0) 收起
回复

使用道具 举报

发表于 2012-10-15 10:05:07 | 显示全部楼层
除了你上面说的,还有在制品,分录一般如下
借:在制品   贷:生产成本转出

配置的话,一般都是OBYC里配的。
本楼点评(0) 收起
回复

使用道具 举报

发表于 2012-10-15 11:28:29 | 显示全部楼层
先马克,学习一下。
本楼点评(0) 收起
回复

使用道具 举报

发表于 2012-10-18 13:13:59 | 显示全部楼层
来看看!
本楼点评(0) 收起
回复

使用道具 举报

发表于 2021-7-20 17:49:12 | 显示全部楼层
好好学习
本楼点评(0) 收起
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 注册

本版积分规则

小黑屋|联系我们|赛跑网 ( QQ:108519493QQfsq

GMT+8, 2024-5-19 09:20 , Processed in 0.285957 second(s), 58 queries .

Powered by 91SAP X3.4

© 2001-2023 91sap Team.

快速回复 返回顶部 返回列表