[FI问题] FI和PS模块的集成点有哪些? |
1赛跑币
最佳答案我在SCN上查到的一段介绍:
When you are creating a project you need controlling area,company code,profit centers,cost centers,settlement profile,costing sheet,RA key,Activity types.PS is working with CO Module directly and then CO is working with FI internally.When every post any entry for a cost element,automatically the corresponding GL is posted.
大意就是你在创建一个工程的时候,你需要用到 ...